NESO called a Turn Down event on 2 Mar 2024, running from 18:00 to 18:30 across 1 half-hour settlement periods. 100.0 MW was procured against a 100.0 MW requirement (100% fill rate), with 18 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
100.0 MW
Procured
100.0 MW
100% of requirement
Bid Cost
£36.0k
Bids
22 / 44
accepted / total
Participants
18
Accepted Volume by Participant
Aggregated across 1 half-hour periods, sorted by accepted volume
All bids rejected (7)
EDF 46.0 MW @ £3000/MWhE.ON 18.0 MW @ £1083/MWhAXLE 10.0 MW @ £2498/MWhOVO 7.0 MW @ £1250/MWhEQUIWATT 5.0 MW @ £1110/MWhFLEXITRICITY 2.0 MW @ £2000/MWhUTILITA 2.0 MW @ £3000/MWh
Half-Hour Periods
18:00
ProcuredSettledReq: 100.0 MW per period
Requirement vs Procured by Period
Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| OCTOPUS ENERGY LIMITED | 40.0 MW40.0 MW rejected | £20.0k | £500/MWh |
| INFINIS LIMITED | 22.0 MW | £20.9k | £950/MWh |
| DRAX ENERGY SOLUTIONS LIMITED | 10.0 MW | £9.2k | £946/MWh |
| OAKTREE POWER LIMITED | 8.0 MW5.0 MW rejected | £5.5k | £610/MWh |
| PERSE TECHNOLOGY LIMITED | 5.0 MW | £4.4k | £899/MWh |
| GRIDIMP LTD | 4.0 MW | £4.0k | £998/MWh |
| URBAN RESERVE (ASSETCO 2) LIMITED | 4.0 MW | £2.0k | £500/MWh |
| GRIDBEYOND LIMITED | 2.0 MW4.0 MW rejected | £2.0k | £1000/MWh |
| SOLO ENERGY LIMITED | 2.0 MW3.0 MW rejected | £1.9k | £950/MWh |
| HILDEBRAND TECHNOLOGY LIMITED | 2.0 MW | £1.5k | £750/MWh |
| LEVELISE LIMITED | 1.0 MW | £670 | £670/MWh |
| EDF ENERGY CUSTOMERS LIMITED | 0.0 MW46.0 MW rejected | £0 | £3000/MWhrej |
| E.ON NEXT ENERGY LIMITED | 0.0 MW18.0 MW rejected | £0 | £1083/MWhrej |
| AXLE ENERGY LIMITED | 0.0 MW10.0 MW rejected | £0 | £2498/MWhrej |
| OVO ELECTRICITY LTD | 0.0 MW7.0 MW rejected | £0 | £1250/MWhrej |
| EQUIWATT LIMITED | 0.0 MW5.0 MW rejected | £0 | £1110/MWhrej |
| FLEXITRICITY LIMITED | 0.0 MW2.0 MW rejected | £0 | £2000/MWhrej |
| UTILITA ENERGY LIMITED | 0.0 MW2.0 MW rejected | £0 | £3000/MWhrej |