NESO called a Turn Down event on 19 Feb 2025, running from 16:00 to 19:00 across 6 half-hour settlement periods. 176.6 MW was procured against a 500.0 MW requirement (35% fill rate), with 11 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
500.0 MW
Procured
176.6 MW
35% of requirement
Bid Cost
£10.9k
Bids
39 / 96
accepted / total
Participants
11
Accepted Volume by Participant
Aggregated across 6 half-hour periods, sorted by accepted volume
All bids rejected (6)
OCTOPUS 281.9 MW @ £165/MWhDRAX 36.0 MW @ £1000/MWhAXLE 13.0 MW @ £642/MWhCUB 6.0 MW @ £595/MWhSSE 3.9 MW @ £490/MWhUTILITA 3.3 MW @ £340/MWh
Half-Hour Periods
16:00
16:30
17:00
17:30
18:00
18:30
ProcuredSettledReq: 500.0 MW per period
Requirement vs Procured by Period
Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| INFINIS LIMITED | 92.0 MW46.0 MW rejected | £12.0k | £130/MWh |
| GRIDBEYOND LIMITED | 57.6 MW46.8 MW rejected | £6.6k | £118/MWh |
| GRIDIMP LTD | 16.0 MW8.0 MW rejected | £2.1k | £130/MWh |
| OAKTREE POWER LIMITED | 8.0 MW10.0 MW rejected | £820 | £103/MWh |
| HILDEBRAND TECHNOLOGY LIMITED | 3.0 MW3.0 MW rejected | £380 | £127/MWh |
| OCTOPUS ENERGY LIMITED | 0.0 MW281.9 MW rejected | £0 | £165/MWhrej |
| DRAX ENERGY SOLUTIONS LIMITED | 0.0 MW36.0 MW rejected | £0 | £1000/MWhrej |
| AXLE ENERGY LIMITED | 0.0 MW13.0 MW rejected | £0 | £642/MWhrej |
| CUB (UK) LTD | 0.0 MW6.0 MW rejected | £0 | £595/MWhrej |
| SSE DIGITAL SERVICES LIMITED | 0.0 MW3.9 MW rejected | £0 | £490/MWhrej |
| UTILITA ENERGY LIMITED | 0.0 MW3.3 MW rejected | £0 | £340/MWhrej |