NESO called a Turn Down event on 10 Jun 2025, running from 18:00 to 20:00 across 4 half-hour settlement periods. 121.7 MW was procured against a 500.0 MW requirement (24% fill rate), with 6 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
500.0 MW
Procured
121.7 MW
24% of requirement
Bid Cost
£6.8k
Bids
27 / 50
accepted / total
Participants
6
Accepted Volume by Participant
Aggregated across 4 half-hour periods, sorted by accepted volume
All bids rejected (3)
GRIDBEYOND 73.6 MW @ £140/MWhEQUIWATT 5.4 MW @ £125/MWhGRIDIMP 4.0 MW @ £160/MWh
Half-Hour Periods
18:00
18:30
19:00
19:30
ProcuredSettledReq: 500.0 MW per period
Requirement vs Procured by Period
Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| INFINIS LIMITED | 112.7 MW | £12.7k | £113/MWh |
| OAKTREE POWER LIMITED | 6.0 MW | £654 | £109/MWh |
| HILDEBRAND TECHNOLOGY LIMITED | 3.0 MW1.0 MW rejected | £328 | £109/MWh |
| GRIDBEYOND LIMITED | 0.0 MW73.6 MW rejected | £0 | £140/MWhrej |
| EQUIWATT LIMITED | 0.0 MW5.4 MW rejected | £0 | £125/MWhrej |
| GRIDIMP LTD | 0.0 MW4.0 MW rejected | £0 | £160/MWhrej |