NESO called a Turn Down event on 16 Jul 2025, running from 18:00 to 22:00 across 8 half-hour settlement periods. 136.9 MW was procured against a 500.0 MW requirement (27% fill rate), with 6 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
500.0 MW
Procured
136.9 MW
27% of requirement
Bid Cost
£7.8k
Bids
38 / 86
accepted / total
Participants
6
Accepted Volume by Participant
Aggregated across 8 half-hour periods, sorted by accepted volume
All bids rejected (3)
OAKTREE 14.0 MW @ £119/MWhEQUIWATT 6.0 MW @ £160/MWhGRIDIMP 4.0 MW @ £160/MWh
Half-Hour Periods
18:00
18:30
19:00
19:30
20:00
20:30
21:00
21:30
ProcuredSettledReq: 500.0 MW per period
Requirement vs Procured by Period
Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| INFINIS LIMITED | 99.3 MW52.9 MW rejected | £11.2k | £112/MWh |
| GRIDBEYOND LIMITED | 33.6 MW33.6 MW rejected | £4.0k | £120/MWh |
| HILDEBRAND TECHNOLOGY LIMITED | 4.0 MW4.0 MW rejected | £462 | £116/MWh |
| OAKTREE POWER LIMITED | 0.0 MW14.0 MW rejected | £0 | £119/MWhrej |
| EQUIWATT LIMITED | 0.0 MW6.0 MW rejected | £0 | £160/MWhrej |
| GRIDIMP LTD | 0.0 MW4.0 MW rejected | £0 | £160/MWhrej |