22 Sep 2026

Turn Down

NESO called a Turn Down event on 22 Sep 2026, running from 17:00 to 22:00 across 10 half-hour settlement periods. 703.5 MW was procured against a 500.0 MW requirement (141% fill rate), with 12 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.

Requirement
500.0 MW
Procured
703.5 MW
141% of requirement
Bid Cost
£93.9k
Bids
192 / 311
accepted / total
Participants
12

Accepted Volume by Participant

Aggregated across 10 half-hour periods, sorted by accepted volume

All bids rejected (1)
DRAX 14.0 MW @ £600/MWh

Half-Hour Periods

17:00
17:30
18:00
18:30
19:00
19:30
20:00
20:30
21:00
21:30
ProcuredSettledReq: 500.0 MW per period

Requirement vs Procured by Period

Participants

ParticipantVolumeCostAvg Price
INFINIS LIMITED
422.9 MW16.4 MW rejected
£123.3k£288/MWh
OCTOPUS ENERGY LIMITED
248.0 MW
£54.6k£220/MWh
HILDEBRAND TECHNOLOGY LIMITED
12.7 MW8.1 MW rejected
£3.8k£299/MWh
ENGIE POWER LIMITED
12.0 MW8.0 MW rejected
£3.5k£293/MWh
EQUIWATT LIMITED
2.6 MW16.6 MW rejected
£910£350/MWh
AXLE ENERGY LIMITED
2.2 MW
£801£364/MWh
Shuffle Energy Limited
1.0 MW
£200£200/MWh
U ENERGY GROUP LIMITED
0.7 MW0.8 MW rejected
£226£309/MWh
GRIDVOLT UK LIMITED
0.6 MW0.8 MW rejected
£201£336/MWh
OAKTREE POWER LIMITED
0.6 MW0.6 MW rejected
£202£336/MWh
Bryt Energy Limited
0.2 MW
£39£193/MWh
DRAX ENERGY SOLUTIONS LIMITED
0.0 MW14.0 MW rejected
£0£600/MWhrej