NESO called a Turn Down event on 23 Jan 2023, running from 17:00 to 18:00 across 2 half-hour settlement periods. 660.7 MW was procured against a 336.0 MW requirement (197% fill rate), with 19 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
336.0 MW
Procured
660.7 MW
197% of requirement
Bid Cost
£1.31m
Bids
66 / 68
accepted / total
Participants
19
Accepted Volume by Participant
Aggregated across 2 half-hour periods, sorted by accepted volume
Half-Hour Periods
17:00
17:30
ProcuredSettledReq: 336.0 MW per period
Requirement vs Procured by Period
Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| OctopusEnergyLimited | 370.8 MW | £1.67m | £4500/MWh |
| GridbeyondLimited | 51.1 MW | £153.2k | £3000/MWh |
| DraxEnergySolutionsLimited | 46.0 MW | £138.0k | £3000/MWh |
| EONNextEnergyLimited | 35.0 MW | £113.0k | £3500/MWh |
| BritishGasTradingLimited | 24.0 MW | £72.0k | £3000/MWh |
| EngiePowerLimited | 22.0 MW | £66.0k | £3000/MWh |
| OaktreePowerLimited | 20.0 MW | £63.3k | £3167/MWh |
| OVOElectricityLtd | 16.0 MW | £48.0k | £3000/MWh |
| SoloEnergyLimited | 16.0 MW | £48.0k | £3000/MWh |
| EDFEnergyCustomersLimited | 15.0 MW | £90.0k | £6000/MWh |
| CUBUKLtd | 12.0 MW | £42.0k | £3500/MWh |
| OrangePowerLTD | 9.4 MW | £37.9k | £4049/MWh |
| PerseTechnologyLimited | 6.8 MW | £20.4k | £3000/MWh |
| ConradEnergyTradingLimited | 4.6 MW | £13.8k | £3000/MWh |
| GridimpLimited | 4.0 MW | £12.0k | £3000/MWh |
| VpowerU8lectricLTD | 2.0 MW | £6.1k | £3000/MWh |
| EquiwattLimited | 2.0 MW | £6.0k | £3000/MWh |
| EvDOTEnergyLtd | 2.0 MW | £6.0k | £3000/MWh |
| ZenobeEnergyLimited | 2.0 MW | £8.5k | £4249/MWh |