11 Feb 2025

Turn Down

NESO called a Turn Down event on 11 Feb 2025, running from 17:00 to 19:00 across 4 half-hour settlement periods. 164.0 MW was procured against a 200.0 MW requirement (82% fill rate), with 9 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.

Requirement
200.0 MW
Procured
164.0 MW
82% of requirement
Bid Cost
£11.9k
Bids
24 / 57
accepted / total
Participants
9

Accepted Volume by Participant

Aggregated across 4 half-hour periods, sorted by accepted volume

All bids rejected (7)
OCTOPUS 269.4 MW @ £250/MWhGRIDIMP 15.6 MW @ £500/MWhAXLE 11.0 MW @ £642/MWhOAKTREE 10.0 MW @ £1111/MWhGALLAGHER 8.0 MW @ £200/MWhCUB 4.0 MW @ £595/MWhUTILITA 3.5 MW @ £340/MWh

Half-Hour Periods

17:00
17:30
18:00
18:30
ProcuredSettledReq: 200.0 MW per period

Requirement vs Procured by Period

Participants

ParticipantVolumeCostAvg Price
INFINIS LIMITED
160.0 MW
£23.2k£145/MWh
HILDEBRAND TECHNOLOGY LIMITED
4.0 MW
£590£148/MWh
OCTOPUS ENERGY LIMITED
0.0 MW269.4 MW rejected
£0£250/MWhrej
GRIDIMP LTD
0.0 MW15.6 MW rejected
£0£500/MWhrej
AXLE ENERGY LIMITED
0.0 MW11.0 MW rejected
£0£642/MWhrej
OAKTREE POWER LIMITED
0.0 MW10.0 MW rejected
£0£1111/MWhrej
GALLAGHER AGGREGATES LIMITED
0.0 MW8.0 MW rejected
£0£200/MWhrej
CUB (UK) LTD
0.0 MW4.0 MW rejected
£0£595/MWhrej
UTILITA ENERGY LIMITED
0.0 MW3.5 MW rejected
£0£340/MWhrej