NESO called a Turn Down event on 7 Apr 2025, running from 19:00 to 21:00 across 4 half-hour settlement periods. 91.2 MW was procured against a 500.0 MW requirement (18% fill rate), with 6 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
500.0 MW
Procured
91.2 MW
18% of requirement
Bid Cost
£5.5k
Bids
26 / 54
accepted / total
Participants
6
Accepted Volume by Participant
Aggregated across 4 half-hour periods, sorted by accepted volume
All bids rejected (4)
OCTOPUS 254.0 MW @ £156/MWhGRIDBEYOND 31.2 MW @ £150/MWhAXLE 11.3 MW @ £642/MWhEQUIWATT 4.0 MW @ £150/MWh
Half-Hour Periods
19:00
19:30
20:00
20:30
ProcuredSettledReq: 500.0 MW per period
Requirement vs Procured by Period
Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| INFINIS LIMITED | 79.2 MW3.0 MW rejected | £9.6k | £119/MWh |
| OAKTREE POWER LIMITED | 12.0 MW8.0 MW rejected | £1.3k | £111/MWh |
| OCTOPUS ENERGY LIMITED | 0.0 MW254.0 MW rejected | £0 | £156/MWhrej |
| GRIDBEYOND LIMITED | 0.0 MW31.2 MW rejected | £0 | £150/MWhrej |
| AXLE ENERGY LIMITED | 0.0 MW11.3 MW rejected | £0 | £642/MWhrej |
| EQUIWATT LIMITED | 0.0 MW4.0 MW rejected | £0 | £150/MWhrej |