NESO called a Turn Down event on 26 Jun 2025, running from 18:00 to 21:00 across 6 half-hour settlement periods. 28.6 MW was procured against a 500.0 MW requirement (6% fill rate), with 6 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
500.0 MW
Procured
28.6 MW
6% of requirement
Bid Cost
£1.4k
Bids
18 / 60
accepted / total
Participants
6
Accepted Volume by Participant
Aggregated across 6 half-hour periods, sorted by accepted volume
All bids rejected (3)
GRIDBEYOND 110.4 MW @ £137/MWhGRIDIMP 6.0 MW @ £160/MWhEQUIWATT 6.0 MW @ £350/MWh
Half-Hour Periods
18:00
18:30
19:00
19:30
20:00
20:30
ProcuredSettledReq: 500.0 MW per period
Requirement vs Procured by Period
Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| INFINIS LIMITED | 18.6 MW12.7 MW rejected | £1.8k | £97/MWh |
| HILDEBRAND TECHNOLOGY LIMITED | 6.0 MW | £617 | £103/MWh |
| OAKTREE POWER LIMITED | 4.0 MW6.0 MW rejected | £420 | £105/MWh |
| GRIDBEYOND LIMITED | 0.0 MW110.4 MW rejected | £0 | £138/MWhrej |
| GRIDIMP LTD | 0.0 MW6.0 MW rejected | £0 | £160/MWhrej |
| EQUIWATT LIMITED | 0.0 MW6.0 MW rejected | £0 | £350/MWhrej |