24 Jul 2025

Turn Down

NESO called a Turn Down event on 24 Jul 2025, running from 18:00 to 21:00 across 6 half-hour settlement periods. 160.7 MW was procured against a 500.0 MW requirement (32% fill rate), with 5 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.

Requirement
500.0 MW
Procured
160.7 MW
32% of requirement
Bid Cost
£8.4k
Bids
44 / 66
accepted / total
Participants
5

Accepted Volume by Participant

Aggregated across 6 half-hour periods, sorted by accepted volume

All bids rejected (2)
GRIDBEYOND 50.4 MW @ £160/MWhGRIDIMP 4.0 MW @ £160/MWh

Half-Hour Periods

18:00
18:30
19:00
19:30
20:00
20:30
ProcuredSettledReq: 500.0 MW per period

Requirement vs Procured by Period

Participants

ParticipantVolumeCostAvg Price
INFINIS LIMITED
140.7 MW
£14.7k£105/MWh
OAKTREE POWER LIMITED
14.0 MW
£1.5k£106/MWh
HILDEBRAND TECHNOLOGY LIMITED
6.0 MW
£655£109/MWh
GRIDBEYOND LIMITED
0.0 MW50.4 MW rejected
£0£160/MWhrej
GRIDIMP LTD
0.0 MW4.0 MW rejected
£0£160/MWhrej