19 Nov 2025

Turn Down

NESO called a Turn Down event on 19 Nov 2025, running from 16:00 to 20:00 across 8 half-hour settlement periods. 182.1 MW was procured against a 500.0 MW requirement (36% fill rate), with 7 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.

Requirement
500.0 MW
Procured
182.1 MW
36% of requirement
Bid Cost
£9.6k
Bids
24 / 57
accepted / total
Participants
7

Accepted Volume by Participant

Aggregated across 8 half-hour periods, sorted by accepted volume

All bids rejected (4)
GRIDBEYOND 24.0 MW @ £165/MWhEQUIWATT 11.4 MW @ £110/MWhGRIDIMP 4.0 MW @ £160/MWhUTILITA 3.0 MW @ £340/MWh

Half-Hour Periods

16:00
16:30
17:00
17:30
18:00
18:30
19:00
19:30
ProcuredSettledReq: 500.0 MW per period

Requirement vs Procured by Period

Participants

ParticipantVolumeCostAvg Price
INFINIS LIMITED
158.1 MW
£16.5k£104/MWh
OAKTREE POWER LIMITED
20.0 MW14.0 MW rejected
£2.2k£111/MWh
GALLAGHER AGGREGATES LIMITED
4.0 MW8.0 MW rejected
£480£120/MWh
GRIDBEYOND LIMITED
0.0 MW24.0 MW rejected
£0£165/MWhrej
EQUIWATT LIMITED
0.0 MW11.4 MW rejected
£0£110/MWhrej
GRIDIMP LTD
0.0 MW4.0 MW rejected
£0£160/MWhrej
UTILITA ENERGY LIMITED
0.0 MW3.0 MW rejected
£0£340/MWhrej