NESO called a Turn Down event on 5 Jan 2026, running from 16:00 to 19:00 across 6 half-hour settlement periods. 149.9 MW was procured against a 500.0 MW requirement (30% fill rate), with 3 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
500.0 MW
Procured
149.9 MW
30% of requirement
Bid Cost
£13.9k
Bids
34 / 36
accepted / total
Participants
3
Accepted Volume by Participant
Aggregated across 6 half-hour periods, sorted by accepted volume
Half-Hour Periods
16:00
16:30
17:00
17:30
18:00
18:30
ProcuredSettledReq: 500.0 MW per period
Requirement vs Procured by Period
Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| INFINIS LIMITED | 98.9 MW | £18.1k | £181/MWh |
| OAKTREE POWER LIMITED | 39.0 MW | £6.6k | £170/MWh |
| GRIDBEYOND LIMITED | 12.0 MW6.0 MW rejected | £3.0k | £250/MWh |