NESO called a Turn Down event on 6 Jan 2026, running from 16:00 to 19:00 across 6 half-hour settlement periods. 220.8 MW was procured against a 500.0 MW requirement (44% fill rate), with 4 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
500.0 MW
Procured
220.8 MW
44% of requirement
Bid Cost
£18.6k
Bids
40 / 40
accepted / total
Participants
4
Accepted Volume by Participant
Aggregated across 6 half-hour periods, sorted by accepted volume
Half-Hour Periods
16:00
16:30
17:00
17:30
18:00
18:30
ProcuredSettledReq: 500.0 MW per period
Requirement vs Procured by Period
Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| INFINIS LIMITED | 135.0 MW | £16.7k | £122/MWh |
| OAKTREE POWER LIMITED | 39.0 MW | £8.1k | £208/MWh |
| EQUIWATT LIMITED | 28.8 MW | £7.9k | £275/MWh |
| GRIDBEYOND LIMITED | 18.0 MW | £4.5k | £250/MWh |