NESO called a Turn Down event on 4 Feb 2026, running from 16:00 to 20:00 across 8 half-hour settlement periods. 198.8 MW was procured against a 500.0 MW requirement (40% fill rate), with 4 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
500.0 MW
Procured
198.8 MW
40% of requirement
Bid Cost
£9.4k
Bids
16 / 49
accepted / total
Participants
4
Accepted Volume by Participant
Aggregated across 8 half-hour periods, sorted by accepted volume
All bids rejected (2)
EQUIWATT 14.4 MW @ £110/MWhUTILITA 3.0 MW @ £340/MWh
Half-Hour Periods
16:00
16:30
17:00
17:30
18:00
18:30
19:00
19:30
ProcuredSettledReq: 500.0 MW per period
Requirement vs Procured by Period
Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| INFINIS LIMITED | 182.8 MW184.0 MW rejected | £17.2k | £94/MWh |
| OAKTREE POWER LIMITED | 16.0 MW32.0 MW rejected | £1.7k | £105/MWh |
| EQUIWATT LIMITED | 0.0 MW14.4 MW rejected | £0 | £110/MWhrej |
| UTILITA ENERGY LIMITED | 0.0 MW3.0 MW rejected | £0 | £340/MWhrej |