NESO called a Turn Down event on 14 Feb 2026, running from 16:00 to 20:00 across 8 half-hour settlement periods. 0.0 MW was procured against a 500.0 MW requirement (0% fill rate), with 2 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
500.0 MW
Procured
0.0 MW
0% of requirement
Bid Cost
£0
Bids
0 / 11
accepted / total
Participants
2
Accepted Volume by Participant
Aggregated across 8 half-hour periods, sorted by accepted volume
All bids rejected (2)
GRIDBEYOND 24.0 MW @ £158/MWhUTILITA 3.0 MW @ £340/MWh
Half-Hour Periods
16:00
16:30
17:00
17:30
18:00
18:30
19:00
19:30
ProcuredSettledReq: 500.0 MW per period
Requirement vs Procured by Period
Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| GRIDBEYOND LIMITED | 0.0 MW24.0 MW rejected | £0 | £158/MWhrej |
| UTILITA ENERGY LIMITED | 0.0 MW3.0 MW rejected | £0 | £340/MWhrej |