NESO called a Turn Up event on 24 May 2026, running from 11:00 to 16:00 across 10 half-hour settlement periods. 0.6 MW was procured against a 500.0 MW requirement (0% fill rate), with 1 participant submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
500.0 MW
Procured
0.6 MW
0% of requirement
Bid Cost
£10
Bids
6 / 10
accepted / total
Participants
1
Accepted Volume by Participant
Aggregated across 10 half-hour periods, sorted by accepted volume
Half-Hour Periods
11:00
11:30
12:00
12:30
13:00
13:30
14:00
14:30
15:00
15:30
ProcuredSettledReq: 500.0 MW per period
Requirement vs Procured by Period
Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| Shuffle Energy Limited | 0.6 MW0.4 MW rejected | £20 | £33/MWh |