NESO called a Turn Down event on 2 Sep 2026, running from 20:00 to 22:00 across 4 half-hour settlement periods. 306.2 MW was procured against a 300.0 MW requirement (102% fill rate), with 11 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
300.0 MW
Procured
306.2 MW
102% of requirement
Bid Cost
£23.9k
Bids
97 / 151
accepted / total
Participants
11
Accepted Volume by Participant
Aggregated across 4 half-hour periods, sorted by accepted volume
All bids rejected (2)
AXLE 23.9 MW @ £298/MWhEQUIWATT 16.0 MW @ £260/MWh
Half-Hour Periods
20:00
20:30
21:00
21:30
ProcuredSettledReq: 300.0 MW per period
Requirement vs Procured by Period
Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| OCTOPUS ENERGY LIMITED | 198.4 MW | £28.8k | £145/MWh |
| INFINIS LIMITED | 49.6 MW | £8.9k | £174/MWh |
| Goonhilly Limited | 17.8 MW | £3.0k | £170/MWh |
| St Breock Limited | 16.9 MW | £2.9k | £170/MWh |
| Sancton Hill Limited | 11.1 MW | £1.9k | £170/MWh |
| ENGIE POWER LIMITED | 8.0 MW | £1.6k | £196/MWh |
| HILDEBRAND TECHNOLOGY LIMITED | 3.6 MW | £603 | £168/MWh |
| Shuffle Energy Limited | 0.4 MW | £68 | £170/MWh |
| U ENERGY GROUP LIMITED | 0.4 MW | £69 | £172/MWh |
| AXLE ENERGY LIMITED | 0.0 MW23.9 MW rejected | £0 | £306/MWhrej |
| EQUIWATT LIMITED | 0.0 MW16.0 MW rejected | £0 | £260/MWhrej |