NESO called 3 Turn Up events on 12 Nov 2026, running from 11:00 to 23:00 across 24 half-hour settlement periods. 433.4 MW was procured against a 1.00 GW requirement (43% fill rate), with 8 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
1.00 GW
Procured
433.4 MW
43% of requirement
Bid Cost
£43.4k
Bids
213 / 356
accepted / total
Participants
8
Accepted Volume by Participant
Aggregated across 38 half-hour periods, sorted by accepted volume
All bids rejected (1)
Bryt 0.4 MW @ £283/MWh
Half-Hour Periods
11:00
11:30
12:00
12:30
13:00
13:30
14:00
14:30
15:00
15:30
16:00
16:30
17:00
17:30
18:00
18:30
19:00
19:30
20:00
20:30
21:00
21:30
22:00
22:30
ProcuredSettledReq: up to 1.00 GW per period
Requirement vs Procured by Period
Req: up to 1.00 GW per period (off scale)Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| OCTOPUS ENERGY LIMITED | 292.3 MW | £58.5k | £200/MWh |
| HILDEBRAND TECHNOLOGY LIMITED | 90.2 MW17.1 MW rejected | £18.0k | £197/MWh |
| ENGIE POWER LIMITED | 32.2 MW | £6.5k | £201/MWh |
| EQUIWATT LIMITED | 14.8 MW | £3.2k | £216/MWh |
| Shuffle Energy Limited | 1.4 MW2.4 MW rejected | £282 | £201/MWh |
| U ENERGY GROUP LIMITED | 1.4 MW | £301 | £215/MWh |
| GRIDVOLT UK LIMITED | 1.1 MW2.1 MW rejected | £199 | £181/MWh |
| Bryt Energy Limited | 0.0 MW0.4 MW rejected | £0 | £283/MWhrej |