NESO called a Turn Down event on 5 Jan 2025, running from 16:00 to 18:00 across 4 half-hour settlement periods. 0.0 MW was procured against a 150.0 MW requirement (0% fill rate), with 3 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
150.0 MW
Procured
0.0 MW
0% of requirement
Bid Cost
£0
Bids
0 / 16
accepted / total
Participants
3
Accepted Volume by Participant
Aggregated across 4 half-hour periods, sorted by accepted volume
All bids rejected (3)
AXLE 26.0 MW @ £642/MWhUTILITA 6.4 MW @ £475/MWhGRIDIMP 4.0 MW @ £500/MWh
Half-Hour Periods
16:00
16:30
17:00
17:30
ProcuredSettledReq: 150.0 MW per period
Requirement vs Procured by Period
Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| AXLE ENERGY LIMITED | 0.0 MW26.0 MW rejected | £0 | £642/MWhrej |
| UTILITA ENERGY LIMITED | 0.0 MW6.4 MW rejected | £0 | £475/MWhrej |