NESO called a Turn Down event on 22 Jan 2025, running from 16:00 to 19:00 across 6 half-hour settlement periods. 607.7 MW was procured against a 500.0 MW requirement (122% fill rate), with 10 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
500.0 MW
Procured
607.7 MW
122% of requirement
Bid Cost
£197.7k
Bids
71 / 81
accepted / total
Participants
10
Accepted Volume by Participant
Aggregated across 6 half-hour periods, sorted by accepted volume
Half-Hour Periods
16:00
16:30
17:00
17:30
18:00
18:30
ProcuredSettledReq: 500.0 MW per period
Requirement vs Procured by Period
Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| INFINIS LIMITED | 246.0 MW | £152.6k | £620/MWh |
| OCTOPUS ENERGY LIMITED | 240.2 MW | £168.1k | £700/MWh |
| GRIDBEYOND LIMITED | 60.0 MW6.0 MW rejected | £42.0k | £700/MWh |
| GRIDIMP LTD | 23.4 MW | £11.7k | £500/MWh |
| AXLE ENERGY LIMITED | 13.0 MW | £8.3k | £642/MWh |
| PERSE TECHNOLOGY LIMITED | 8.4 MW | £4.2k | £500/MWh |
| CUB (UK) LTD | 6.0 MW | £3.0k | £500/MWh |
| UTILITA ENERGY LIMITED | 4.7 MW | £1.6k | £340/MWh |
| OAKTREE POWER LIMITED | 4.0 MW8.0 MW rejected | £2.4k | £599/MWh |
| EQUIWATT LIMITED | 2.0 MW | £1.3k | £650/MWh |