NESO called a Turn Down event on 17 Apr 2026, running from 16:00 to 23:00 across 14 half-hour settlement periods. 137.0 MW was procured against a 500.0 MW requirement (27% fill rate), with 2 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
500.0 MW
Procured
137.0 MW
27% of requirement
Bid Cost
£7.4k
Bids
43 / 69
accepted / total
Participants
2
Accepted Volume by Participant
Aggregated across 14 half-hour periods, sorted by accepted volume
All bids rejected (1)
EQUIWATT 19.4 MW @ £225/MWh
Half-Hour Periods
16:00
16:30
17:00
17:30
18:00
18:30
19:00
19:30
20:00
20:30
21:00
21:30
22:00
22:30
ProcuredSettledReq: 500.0 MW per period
Requirement vs Procured by Period
Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| INFINIS LIMITED | 137.0 MW21.7 MW rejected | £14.7k | £108/MWh |
| EQUIWATT LIMITED | 0.0 MW19.4 MW rejected | £0 | £225/MWhrej |