NESO called a Turn Down event on 8 Sep 2026, running from 17:00 to 22:00 across 10 half-hour settlement periods. 189.2 MW was procured against a 500.0 MW requirement (38% fill rate), with 9 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.
Requirement
500.0 MW
Procured
189.2 MW
38% of requirement
Bid Cost
£16.2k
Bids
208 / 233
accepted / total
Participants
9
Accepted Volume by Participant
Aggregated across 10 half-hour periods, sorted by accepted volume
All bids rejected (2)
AXLE 23.0 MW @ £319/MWhDRAX 13.8 MW @ £1500/MWh
Half-Hour Periods
17:00
17:30
18:00
18:30
19:00
19:30
20:00
20:30
21:00
21:30
ProcuredSettledReq: 500.0 MW per period
Requirement vs Procured by Period
Participants
| Participant | Volume | Cost | Avg Price |
|---|---|---|---|
| INFINIS LIMITED | 160.9 MW | £27.1k | £168/MWh |
| EQUIWATT LIMITED | 16.0 MW | £3.2k | £203/MWh |
| HILDEBRAND TECHNOLOGY LIMITED | 9.1 MW | £1.6k | £171/MWh |
| U ENERGY GROUP LIMITED | 1.3 MW0.1 MW rejected | £236 | £183/MWh |
| Shuffle Energy Limited | 1.0 MW | £175 | £175/MWh |
| OAKTREE POWER LIMITED | 0.8 MW | £150 | £188/MWh |
| Bryt Energy Limited | 0.1 MW | £15 | £150/MWh |
| AXLE ENERGY LIMITED | 0.0 MW23.0 MW rejected | £0 | £319/MWhrej |
| DRAX ENERGY SOLUTIONS LIMITED | 0.0 MW13.8 MW rejected | £0 | £1500/MWhrej |