28 Oct 2026

Turn UpTurn DownTurn DownTurn Up

NESO called a Turn Up event on 28 Oct 2026, running from 16:00 to 16:00 across 36 half-hour settlement periods. 525.6 MW was procured against a 500.0 MW requirement (105% fill rate), with 8 participants submitting bids. The merit order chart below shows accepted and rejected volumes by participant, sorted by who delivered the most.

Requirement
500.0 MW
Procured
525.6 MW
105% of requirement
Bid Cost
£52.5k
Bids
189 / 400
accepted / total
Participants
8

Accepted Volume by Participant

Aggregated across 36 half-hour periods, sorted by accepted volume

All bids rejected (3)
OCTOPUS 442.5 MW @ £177/MWhEQUIWATT 22.2 MW @ £312/MWhGRIDVOLT 1.9 MW @ £45/MWh

Half-Hour Periods

16:00
16:30
17:00
17:30
18:00
18:30
19:00
19:30
20:00
20:30
16:00
16:30
17:00
17:30
18:00
18:30
19:00
19:30
20:00
20:30
21:00
21:30
22:00
22:30
15:00
15:30
11:00
11:30
12:00
12:30
13:00
13:30
14:00
14:30
15:00
15:30
ProcuredSettledReq: 500.0 MW per period

Requirement vs Procured by Period

Participants

ParticipantVolumeCostAvg Price
INFINIS LIMITED
255.4 MW
£55.5k£213/MWh
DRAX ENERGY SOLUTIONS LIMITED
245.0 MW
£44.1k£180/MWh
HILDEBRAND TECHNOLOGY LIMITED
22.9 MW17.7 MW rejected
£4.9k£210/MWh
Shuffle Energy Limited
1.4 MW2.2 MW rejected
£280£200/MWh
U ENERGY GROUP LIMITED
0.9 MW
£196£218/MWh
OCTOPUS ENERGY LIMITED
0.0 MW442.5 MW rejected
£0£186/MWhrej
EQUIWATT LIMITED
0.0 MW22.2 MW rejected
£0£312/MWhrej
GRIDVOLT UK LIMITED
0.0 MW1.9 MW rejected
£0£45/MWhrej